to be honest my teacher is ALWAYS telling us that Work done in a Wire *as in Strain Energy* is measured as follows ;
Work done = 0.5*force*extension.
When to use this ,is whenever they ask your for Work Done in a material that has elastic potential energy in it *in this case Spring*.
Hence,
Work done = 0.5 *force * extension *
5 blue ; cuz there are FIVE springs
= 0.5 *(60) * ( 0.5) *
5 = 0.5 * (30) * (5)
= 0.5 * 150
= 75 J good luck to u too